St. Croix Falls Hydro Generation Station

Date: Monday, July 13, 2020
Time: 1:00 PM – 5:00 PM (bus will begin loading at 12:30 PM and will depart at 1:00 PM)
Registration Limit: 40
Cost: $50

Description: The 25.9-MW St. Croix Falls Hydro Generating Station features a powerhouse containing eight turbine-generator units. It was completed in 1905 on the St. Croix River (a National Scenic Riverway) along the Wisconsin-Minnesota border. This operates as partial peaking plant and is the only existing dam on the river. St. Croix Falls as built to provide electricity for the Twin Cities. A feature that separates St. Croix Falls from other hydro facilities is its S-shaped spillway, constructed as a curve to increase its crest area because the river at that spot forms a gorge through which passes a large volume of water.

Restrictions: All attendees should wear closed-toe shoes and comfortable clothing.  Attendees should be able to walk up and down stairways.  No photography or video will be allowed inside of the plant.